Agile & adaptive
⏱ ~3-min readAceMark GuideWhat this topic is really about
The Definition of Done is a formal description of the state of the product increment when it meets the quality measures required for the project. It must be a shared understanding among the Scrum Team to ensure transparency, rather than being dictated by management or varying by individual developer.
A Work-in-Progress (WIP) limit restricts the maximum number of active tasks in a workflow column, which helps teams identify bottlenecks and optimize flow. Distractors like sprint length are incorrect because Kanban is a continuous flow system rather than a timeboxed sprint system like Scrum.
See the mechanism
According to the Scrum Guide, a sprint is a timeboxed event of one month or less, making four weeks the maximum recommended duration to maintain focus and limit risk. A diagram for this topic isn't available yet — the worked example below walks the same reasoning step by step.
An exam-style question, fully explained
In Scrum, the maximum recommended length of a sprint is:
- Identify what the question tests: In Scrum, the maximum recommended length of a sprint is:.
- According to the Scrum Guide, a sprint is a timeboxed event of one month or less, making four weeks the maximum recommended duration to maintain focus and limit risk.
- Option D is incorrect because a twelve-week cycle is far too long, reducing the team's ability to adapt to changes quickly.
Traps the examiner sets
- Option D is incorrect because a twelve-week cycle is far too long, reducing the team's ability to adapt to changes quickly.
- Longer options like 30 minutes or 1 hour are incorrect because they encourage detailed problem-solving rather than a quick daily alignment.
- Managing the team is incorrect because Scrum teams are self-managing and do not have a traditional manager directing their daily tasks.
- Distractors like sprint length are incorrect because Kanban is a continuous flow system rather than a timeboxed sprint system like Scrum.